Espanola council approves design plans for the bridge

The Black Creek Bridge replacement project is moving forward.

Espanola council has unanimously agreed to have the final detailed design plans completed for $208,000.

This process is expected to take 17 weeks and construction is estimated at 12-16 weeks.

It is anticipated that the full cost of the design and construction can be 100% funded by the Ontario Community Infrastructure Funding allocations as there are approximately three years outstanding for a total of $819,500.