Elliot Lake Ruben Yli-Juuti Centre pool reconstruction set to be completed in early Spring 2024 

By Rosalind Russell – Reconstruction of the city pool in Elliot Lake is progressing well and is tentatively set to be completed by early Spring 2024. 

In its report, the city says demolition work and excavation are complete, and work is now underway on the pool shell in anticipation of plumbing and liner installation, as well as form work on the deck walls and line market storage, a new pool liner and finishes. 

Several mechanical upgrades are also underway. 

The contractor has reported that if all goes well and there are no supply chain issues, the work should be completed by the last week of March 2024. 

Photo: The repair work on the Elliot Lake public pool, the Ruben Yli-Juuti Aquatics Centre, is being carried out in three separate phases with the hope that all the work will be completed by the early Spring of 2024. Photo provided by Kate Anger – Pool Staffer and used with permission.